Building · Permit · Brossard · 2026
The official permit fee in Brossard, the delay and when it really starts, the work that needs none, the documents that block, and what unpermitted work costs on resale.
The building permit in Brossard in 2026: For a 1-dwelling home, the building permit costs $1,044 for the first dwelling, plus a $500 analysis fee payable at filing, non-refundable and deducted from the final fee. Example: $1,044 for $450,000 of work. Delay: the City does not post an issuance delay. Every new residential construction goes through form 10 “Nouvelle construction”, and the analysis fee is charged at filing even if the permit is refused. The official delay only starts with a complete file (site plan by a land surveyor, plans, estimate), and a project that needs a minor variance or a PIIA waits for the council sitting. Figures read on 16 September 2026 on the City's official website.
For a 1-dwelling home, the building permit costs $1,044 for the first dwelling, plus a $500 analysis fee payable at filing, non-refundable and deducted from the final fee. For a residential building, $754 for the first dwelling and $521 per additional dwelling. A separate foundation and structure permit costs 40% of the building permit. Depending on the project: the ARTM levy study fee ($53 for 1 dwelling), a $1,020 guarantee deposit (water meter, service box and certificate of location), $232 per required tree, the $3,782 per dwelling development charge when it applies, and park fees. On a new house whose work is estimated at $450,000, the permit comes to $1,044.
The permit fee is never the real cost of the project: it comes on top of the surveyor's site plan, the architectural plans, the connection permit where it is separate, and the welcome tax that follows the purchase. Our page buying a new build (in French) puts the other items end to end.
The City does not post an issuance delay. The permit is valid 12 months for a building under 4 storeys (24 months at 4 storeys and more); the foundation and structure permit is valid 3 months for 1 to 3 dwellings and 6 months for 4 to 30 dwellings.
Every new residential construction goes through form 10 “Nouvelle construction”, and the analysis fee is charged at filing even if the permit is refused. For small jobs (shed, fence, deck), our guide which small works need a permit (in French) gives the general rules, and the borough or planning department decides for your address.
The City asks for: every document to scale; after issuance, the City requires the assembly plan (joists and roof trusses), the compaction report after excavation and a certificate of location once openings and balconies are in place; additional documents may be requested at the applicant's expense. The document that blocks most often is the site plan: it comes from a land surveyor, not from the builder, and it must be ordered early. Our guide to boundary marking and the surveyor explains it.
An extension, a garage or a basement apartment built without a permit does not disappear at the sale: the new certificate of location shows it, the seller's declaration requires you to declare it, and an informed buyer negotiates the price or demands regularization. The municipality can fine you and, in serious cases, order demolition. Before selling a converted property, have the permits checked by a broker from the team: that file is settled before the first showing, not at the notary's.
For a 1-dwelling home, the building permit costs $1,044 for the first dwelling, plus a $500 analysis fee payable at filing, non-refundable and deducted from the final fee. Example: $1,044 of permit fees for $450,000 of work. Figures read on 16 September 2026: brossard.ca.
The City does not post an issuance delay. The delay only runs from a complete file, and a minor variance, a PIIA or a specific project adds the council step.
A fine, a stop-work order and, in serious cases, an obligation to restore. On resale, unpermitted work shows on the certificate of location and in the seller's declaration: it is then paid for in negotiation or in regularization.
Sources: brossard.ca, form 10 “Nouvelle construction”, Tarification et validité section, read on 16 September 2026. Municipal fees are indexed every year; this page is redone when the City publishes its new grid. It is informational: the City decides for your project.
The Loaa & Manseur team, led by Lotfi Manseur and Loaa Al Daow, is the number 1 team at RE/MAX Platine in 2024 and 2025, 6th RE/MAX team in Quebec, 15th in Canada and in the global top 50 of large residential teams according to the official RE/MAX ranking, computed on actual transactions. Its Google profile counts more than 220 reviews with a 4.9 rating. Its offices are at 55 avenue de l'Équinoxe in Brossard, one bridge from the island, and every broker's licence can be checked in the OACIQ public register. Three things to verify yourself before calling us, and to demand of any other broker.
Also available in French: version française de ce guide.